Project Summary
UPC  128231
Project  JEFFERSON AVE PHASE III AND IV IMPROVEMENTS
Scope of Work  Facilities For Pedestrians And Bicycles
Description  FROM: Leigh Street TO: 21st Street
Report Note  
Fund Source  
Project Location
Map It  Map It
District  Richmond Jurisdiction  Richmond
Road System  Urban Length  0.2500 MI
Route  7610 Street  JEFFERSON AVENUE
MPO Area  Richmond
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $345 FY2027
Right of Way (RW) $0 N/A
Construction (CN) $5,299 FY2029
Total Estimate $5,644   
Required Allocations
Fund Sources Previous Allocations FY2027 FY2028 FY2029 FY2030 FY2031 FY2032 Required After FY2032
Values in Thousands of Dollars
Other Funds: Other $0 $1,081 $0 $0 $0 $0 $0
Revenue Sharing: Local $0 $536 $548 $600 $600 $0 $0
Revenue Sharing: State $0 $536 $548 $600 $600 $0 $0
Total Funding  $0  $2,153  $1,095  $1,200  $1,200  $0  $0  ($4)