Project Summary
UPC  121389
Project  EASTERN AVE SOUTH CONNECTION REVENUE SHARING
Scope of Work  New Construction Roadway
Description  FROM: West Hall Drive TO: Route 250
Report Note  
Fund Source  
Project Location
Map It  Map It
District  Culpeper Jurisdiction  Albemarle County
Road System  Secondary Length  0.5800 MI
Route  9999 Street  Eastern Avenue South Connection
MPO Area  Charlottesville
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $2,707 Underway
Right of Way (RW) $1,825 FY2028
Construction (CN) $34,943 FY2029
Total Estimate $39,475   
Required Allocations
Fund Sources Previous Allocations FY2027 FY2028 FY2029 FY2030 FY2031 FY2032 Required After FY2032
Values in Thousands of Dollars
Revenue Sharing: Local $8,121 $0 $0 $0 $0 $0 $0
Revenue Sharing: State $8,121 $0 $0 $0 $0 $0 $0
Total Funding  $16,242  $0  $0  $0  $0  $0  $0  $23,233