Project Summary
UPC  17534
Project  RTE 58 - CORRIDOR DEVELOPMENT PROG - 4 LANES (CROOKED OAK)
Scope of Work  Reconstruction w/ Added Capacity
Description  FROM: 0.131 KILOMETER WEST ROUTE 820 TO: 0.492 KILOMETER EAST BIG REED ISLAND CREEK
Report Note  Route 58 Corridor Program
Fund Source  BOND
Project Location
Map It  Map It
District  Salem Jurisdiction  Carroll County
Road System  Primary Length  11.5060 KM
Route  0058 Street  
MPO Area  NonMPO
Zip Code  24325
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $7,850 Complete
Right of Way (RW) $7,850 Complete
Construction (CN) $152,800 Underway
Total Estimate $168,500   
Required Allocations
Fund Sources Previous Allocations FY2020 FY2021 FY2022 FY2023 FY2024 FY2025 Required After FY2025
Values in Thousands of Dollars
Specialized State and Federal: Bond $3,875 $8,696 $26,000 $0 $121,483 $0 $0
Specialized State and Federal: State $8,446 $0 $0 $0 $0 $0 $0
Total Funding  $12,321  $8,696  $26,000  $0  $121,483  $0  $0  $0