Project Summary
UPC  113176
Project  WEST MAIN ST. PHASE I - RIDGE ST. TO 6TH ST. NW
Scope of Work  Facilities for Pedestrians and Bicycles
Description  FROM: RIDGE STREET TO: 6TH STREET NW
Report Note  
Fund Source  REVSH
Project Location
Map It  Map It
District  Culpeper Jurisdiction  Charlottesville
Road System  Urban Length  0.1900 MI
Route  9999 Street  WEST MAIN STREET
MPO Area  NonMPO
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $588 Complete
Right of Way (RW) $500 Complete
Construction (CN) $11,500 Underway
Total Estimate $12,588   
Required Allocations
Fund Sources Previous Allocations FY2020 FY2021 FY2022 FY2023 FY2024 FY2025 Required After FY2025
Values in Thousands of Dollars
Other Funds: Other $6,036 $0 $0 $0 $0 $0 $0
Revenue Sharing: Local $3,276 $0 $0 $0 $0 $0 $0
Revenue Sharing: State $3,276 $0 $0 $0 $0 $0 $0
Total Funding  $12,588  $0  $0  $0  $0  $0  $0  $0