Project Summary
UPC  105782
Project  RTE. 613 OVER RAPPAHANNOCK RIVER BRIDGE REHABILITATION
Scope of Work  Bridge Rehab w/o Added Capacity
Description  FROM: 0.0 mi. from Culpeper Co. Line TO: 0.0 mi. from Fauquier Co. Line
Report Note  Current fund type covers bridge replacement only and will be removed from this rehabilitation project. Estimate will be revised based on localities’ decision on project scope.
Fund Source  
Project Location
Map It  Map It
District  Culpeper Jurisdiction  Culpeper County
Road System  Secondary Length  0.1000 MI
Route  0613 Street  
MPO Area  NonMPO
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $1,200 Complete
Right of Way (RW) $250 Complete
Construction (CN) $7,600 Underway
Total Estimate $9,050   
Required Allocations
Fund Sources Previous Allocations FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 Required After FY2021
Values in Thousands of Dollars
CTB Formula: Bridge - State $0 $0 $0 $0 $0 $927 $0
STP: BROS - Federal $0 $0 $0 $0 $0 $218 $0
STP: BROS - Soft Match $0 $0 $0 $0 $0 $55 $0
Total Funding  $0  $0  $0  $0  $0  $1,200  $0  $7,850