Line Item Details

Project Summary
UPC  100947
Project  JAMESTOWN FERRY BOAT
Scope of Work  Ferry boats
Description   (_)
Report Note  
Fund Source  
Project Location
Map It  Map It
District  Hampton Roads Jurisdiction  Hampton Roads District-wide
Road System  Primary Length  _
Route  FBJT Street  
MPO Area  NonMPO
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $2,500 Complete
Right of Way (RW) $0 N/A
Construction (CN) $25,087 Complete
Total Estimate $27,587   
Required Allocations
Fund Sources Previous Allocations FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 Required After FY2017
Values in Thousands of Dollars
CMAQ TERMS: Federal $2,000 $0 $0 $0 $0 $0 $0
CMAQ TERMS: State Match $500 $0 $0 $0 $0 $0 $0
Federal STP: Federal $0 $0 $4,106 $6,791 $4,669 $4,503 $0
Soft Match: Federal $0 $0 $1,026 $1,698 $1,167 $1,126 $0
Total Funding  $2,500  $0  $5,132  $8,489  $5,837  $5,629  $0  $0