UPC |
85708 |
Project |
RTE. 29/250 BYPASS INTERCHANGE IMP (HYDRAULIC RD - BARRACKS) |
Scope of Work |
RECONSTR. WITH ADDED CAPACITY |
Description |
FROM: 0.42 mi south of N.C.L. Charlottesville TO: Intersection at Hydraulic Road |
Report Note |
Urban Construction Initiative Project. State Funds - AC for future conversion |
Fund Source |
STPREVSH |
Map It
|
District |
Culpeper |
Jurisdiction |
Charlottesville |
Road System |
Urban |
Length |
0.4200 MI |
Route |
0029 |
Street |
Emmet Street |
MPO Area |
Charlottesville |
|
Prelim. Eng. (PE) |
$517 |
Complete |
Right of Way (RW) |
$0 |
N/A |
Construction (CN) |
$4,183 |
Complete |
Total Estimate |
$4,700 |
  |
|
(X)Revenue Sharing Funds: Local Match |
$1,000 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|
(X)Revenue Sharing Funds: State Match |
$1,000 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|
Primary Formula: State |
$2,200 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|
Total Funding |
$4,200 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
$500 |
|