Project Summary
UPC  17536
Project  RTE 58 - CORRIDOR DEVELPMENT PROG - 4 LANES (LOVERS LEAP)
Scope of Work  Reconstruction w/ Added Capacity
Description  FROM: 0.660 KM EAST ROUTE 714 TO: STUART BYPASS
Report Note  Route 58 Corridor Program
Fund Source  BOND
Project Location
Map It  Map It
District  Salem Jurisdiction  Patrick County
Road System  Primary Length  7.8000 MI
Route  0058 Street  
MPO Area  NonMPO
Zip Code  24120
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $8,750 Complete
Right of Way (RW) $8,750 Complete
Construction (CN) $240,800 Complete
Total Estimate $258,300   
Required Allocations
Fund Sources Previous Allocations FY2020 FY2021 FY2022 FY2023 FY2024 FY2025 Required After FY2025
Values in Thousands of Dollars
Specialized State and Federal: Bond $5,207 $102,712 $138,088 $0 $0 $0 $0
Specialized State and Federal: State $12,293 $0 $0 $0 $0 $0 $0
Total Funding  $17,500  $102,712  $138,088  $0  $0  $0  $0  $0