UPC |
113176 |
Project |
WEST MAIN ST. PHASE I - RIDGE ST. TO 6TH ST. NW |
Scope of Work |
Facilities for Pedestrians and Bicycles |
Description |
FROM: RIDGE STREET TO: 6TH STREET NW |
Report Note |
|
Fund Source |
REVSH |
Map It
|
District |
Culpeper |
Jurisdiction |
Charlottesville |
Road System |
Urban |
Length |
0.1900 MI |
Route |
9999 |
Street |
WEST MAIN STREET |
MPO Area |
NonMPO |
|
Prelim. Eng. (PE) |
$588 |
Complete |
Right of Way (RW) |
$500 |
Complete |
Construction (CN) |
$11,500 |
Complete |
Total Estimate |
$12,588 |
  |
|
Other Funds: Other |
$6,036 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|
Revenue Sharing: Local |
$3,276 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|
Revenue Sharing: State |
$3,276 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|
Total Funding |
$12,588 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
$0 |
|