VDOT Logo Six-Year Improvement Program
Home User's Guide About
Line Item Details

Project Summary
UPC  111705
Project  I-95 AND WILLIS RD INTERCHANGE IMPROVEMENTS
Scope of Work  Safety
Description  FROM: NORTH OF INTERCHANGE TO: SOUTH OF INTERCHANGE
Report Note  
Fund Source  
Project Location
Map It  Map It
District  Richmond Jurisdiction  Chesterfield County
Road System  Interstate Length  0.0900 MI
Route  0095 Street  i-95
MPO Area  Richmond
Estimates & Schedule
Estimated Cost
(Thousands)
Schedule
Prelim. Eng. (PE) $3,800 Complete
Right of Way (RW) $3,200 Complete
Construction (CN) $40,000 Complete
Total Estimate $47,000   
Required Allocations
Fund Sources Previous Allocations FY2020 FY2021 FY2022 FY2023 FY2024 FY2025 Required After FY2025
Values in Thousands of Dollars
Specialized State and Federal: State $5,000 $0 $0 $0 $0 $0 $0
Total Funding  $5,000  $0  $0  $0  $0  $0  $0  $42,000